| Sector | Name of Scheme | Project Cost | Amount Cleared in 1st phase | Name of I/As | Total Amount placed with I/As |
Amount
Utilised
(Rs. in lakhs) |
Physical Target | Physical Status | Remarks | Target Date | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | ||
| Social Infrastructure/ Health | Construction of 11nos. Health Sub-Centres (Cleared for 5 Nos.at Mainama, Machuria, Nalicharra, Bagaichari & Salema) | 110.00 | 55.00 | EE.RD. DLI | 24.96 | 17.25 | Const. of Nalicharra, Salema & Bagaichari Health Sub-centre with driking water sources | 1) Civil works of Nalicherra and Salema Sub-centre completed & creation of drinking water sources in progress. 2) 76% Civil works of Bagaicheri Sub-centre completed. | Patients from 12 nos. remote villages covering 6000 nos families will get medical treatment. | By 15th November, 2005 | ||
| EE. PWD. ADC | 15.51 | 15.51 | Const. of Mainama & Machuria Health Sub-centre with driking water sources | 1) Sub-centre at Mainama already handed over & Machuria to be handed over by this month. 2) Creation of drinking water source in Mainama completed & at Machuria in progress. | Patients from 8 nos. remote villages covering 4000 nos families will get medical treatment. | By 15th November, 2005 | ||||||
| CMO | 3.74 | 2.56 | Procurement furniture & equipment for Mainama, Machuria, Salema, Bagaichari & Nalicharra Health Sub-centres | Supply order for procurement of Furniture & equipments for 5 nos. sub-centres done. | By 15th November, 2005 | |||||||
| Other Infrastructure (Social Amenities & Public Utilities) | Construction of Motor stand at Ambassa | 201.20 | 100.00 | EE. PWD. ABS. | 100.00 | 1.71 | (1) Terminal building, (2) Hard Stand for light vehicle and internal road, (3) Drainage, (4) Boundary wall. | Modified drawing received; Tender for const. of motor stand at Ambassa is to be invited on receipt of modified DNIT. Work order for const. of boundary wall awarded. | Will create better marketting facilities for vendors and dormitory facilities for travellers; will help in smooth traffic movement and improvement of awareness among the public on socio-economic issues. | By December, 2006 | ||
| Construction of Market shed at Ambassa | 12.00 | 12.00 | EE. RD. DLI | 12.00 | 11.08 | Const. of 20 Nos. Market Stall at Ambassa | Civil work at Ambassa Market completed and handed over. | 19 nos. small traders have been benefitted and revenue collection of Govt. through monthly rent is ensured. | Completed | |||
| Construction of Pucca drain at Ambassa market | 2.63 | 2.63 | EE. RD. DLI | 2.63 | 2.42 | Const. of 80 mtrs. Pucca drain around Ambassa market | Pucca drain around Ambassa Market shed Completed. | Drainage and channel facilities of Ambassa Market up-graded. | By 15th November, 2005 | |||
| POWER | a) Intensive Electrification in the electrified hamlets/habitation/paras. | 76.38 | 38.19 | EE, Power, ABS | 38.19 | 37.81 | 11 KV line on P.C.C. Pole-12 KM. | Intensive electrification in 25 Nos. para/hamlets covering 17.80 KMs completed. 9 Nos. para unser SLM-block; 3 Nos. para under DBN-block; 2 Nos. para under MNU-block and 11 Nos. para under ABS-block. | 2000 Mandays generated by enlistment of labourers during execution of works; Agricultural productivity increased by setting up of Irrigation pump; infrustructure created for setting up cottage industries, mini Industry, welding & steel fabrication unit and thereby poverty tend to be reduced by direct engagement in such profession where electricity is essential. Thus, 8000 (approx) people may be uplifted from below poverty line. | |||
| L.T. Line on P.C.C. Pole-28 KM. | ||||||||||||
| 63 KVA distribution substation-2 Nos.. | ||||||||||||
| 25 KVA distribution substation- 4 Nos. | ||||||||||||
| b) Electrification of unelectrified hamlets/habitation/paras(on P.C.C. pole) | 106.41 | 53.205 | EE, Power, ABS | 53.205 | 45.95 | 11 KV line on P.C.C. Pole-34 KM. | Electrification in 4 Nos.un-electrified hamlets(Rangicharra-under Bileshcherra G/P, Malirai Rouja Para-under Mandhi G/P of Salema Block, Brindajoy Reang Para-under Kachimcherra G/P of Ambassa Block & Kacharicharra-under Malidhar G/P of CMN Block done | |||||
| L.T. Line on P.C.C. Pole-18 KM. | ||||||||||||
| 63 KVA distribution substation-10 Nos. | ||||||||||||
| 25 KVA distribution substation-4 Nos.. | ||||||||||||
| c) Electrification of un-electrified hamlets/habitation/paras(on steel tubular pole) | 41.89 | 20.945 | EE, Power, ABS | 20.945 | 8.00 | 11 KV line on steel tubular Pole. | Store component procured. Works programmes to be started in 2nd Phase | |||||
| L.T. Line on steel tubular Pole. | ||||||||||||
| 25 KVA distribution substation. | ||||||||||||
| d) Construction of 63 KVA Distribution sub-station at the load centre including extention of 11 KV line | 21.78 | 10.89 | EE, Power, ABS | 10.89 | 28.18 | 11 KV line on P.C.C. Pole | Construction of 18 Nos. new sub-station including extention of 11 KV line completed | |||||
| 63 KVA distribution substation. | ||||||||||||
| e) Procurement of Computer and Office Automation | 3.54 | 1.77 | EE, Power, ABS | 1.77 | 1.44 | 1 No. | Fax & Photo Copier installed | |||||
| Agriculture & Allied Activities/ Forest | Establishment of Central Nursery for afforestration | 49.10 | 25.00 | DFO. ABS | 12.50 | 3.94 | 75 Hect | 400 mtr. Approach road with side drain to Ambassa central Nursery done. 261 Mtrs. GI barbed wire fencing around central Nursery completed. | Substantial increase in income of individuals and increase in forestry output. | By Decemer, 2005 | ||
| DFO. MNU | 12.50 | 9.36 | 76 Hect | 44 hect. Permanent Nursery beds and 0.57 Nos. Poly bag seedlings raised in Manu Central Nursery | By Decemer, 2005 | |||||||
| Scheme for rejuvenation of the bamboo resource in the forest land | 15.90 | 15.90 | DFO. ABS | 7.95 | 1.55 | 77 Hect | 95 hect. Erected | By Decemer, 2005 | ||||
| DFO. MNU | 7.95 | 0.86 | 78 Hect | 50 hect. Bamboo plantation done at Manu. | By Decemer, 2005 | |||||||
| Industry | Seri-culture development [ Construction of 3 no. of Mulbarry ExtensionService Centre (MESC) at kulai, Halahali & Harerkhola | 17.00 | 17.00 | GM. DIC, DLI | 17.00 | 5.03 | i) Const. of MRCS - 3 units ii) Chawki Garden Development- 3 units iii) Rearing equipments for Chawki silk worm rearing - 3 units iv) Const. of Cocoon preservation room/stiffing room/Cocoon drying platform | (1) Const. of building for Mulbarry ExtensionService Centre (MESC) at Kulai nearly completed. (2) Mobalisation of materials at working sites completed & civil works are taken up for Halahali & Harerkhola MESC.(3) Construction of cocoon preservation & shielding room, cocoon drying platform at Halahali started. | 700 nos beneficiaries will be directly involved in the process of cocoon production activity. 100-120 Kgs. Cocoon production per beneficiary is expected. Rs. 10000 - 12000 individual earning by selling cocoon is expected. | By October, 2005 | ||
| Industry | Tea processing | 100.00 | 25.00 | GM. DIC, DLI | 25.00 | 0.00 | i) Plant & Machinery & Civil works of the factory | Const. of civil work in progress by NEC fund. Due to objection of Planning Commission, fund could not be utilized without arranging credit facility for the cooperative. The tea growers cooperative is being motivated to take bank loan. | 800 garden workers employed. Cooperative Tea Workers will be in a position to sustain themselves by means of selling their green leave to this factory. | |||
| Sub-Total:- | 757.83 | 377.53 | 366.74 | 192.64 | ||||||||
| Communication/Roads & Bridges | Upgradation of road from Tuichakma to Raishyabari under Dumbarnagar Block (Length-19.00 km) | 349.70 | 349.70 | EE. PWD. ABS. | 349.70 | 115.07 | Up-gradation of road -19.00 KM alongwith brick soling, retaining wall etc. | 80% Widening, 10 nos CD, 72.10 mtrs. retaining wall & 3 KM soling completed. | 21 Nos. remote habitation will be connected with Sub-divisional & Block H/Q. Maketing facilities of fish as well as Agri. Products and movement of security personnel in boarder ares will serve. | By December, 2006 | ||
| Communication/Roads & Bridges | Construction of 24-R loading steel Bailey bridge over Dulucherra on the road from K.A.(Rakhal tali to Kashipunji) under Salema Block(Span 120'-0'') | 50.00 | 50.00 | EE. PWD. ABS. | 50.00 | 44.75 | Const. of 1 No. 24-R loading steel Bailey bridge(Span-120'-0") alongwith approach road | Completed | 3 Nos. remote habitation will be connected with district H/Q via Sub-divisional & Block H/Q. | |||
| Construction of 24-R loading Portable steel Bailey bridge over Dulaicherra on the road from K.A.(Near Kulai H.S. School to Gantacherra) under Ambassa Block(Span 150'-0'') | 74.44 | 74.44 | EE. PWD. ABS. | 74.44 | 67.80 | Const. of 1 No. 24-R loading steel Bailey bridge(Span-150'-0") alongwith approach road | Launching of bridge completed. Works of approach road in progress. | 3 Nos. remote habitation will be connected with district H/Q via Sub-divisional & Block H/Q. | By 15th October, 2005 | |||
| Construction of 24-R loading Portable steel Bailey bridge over Sarma River at Bankarghat on the road from Gandacherra to Dhalajari under Dumburnagar Block(Span 150'-0'') | 88.65 | 88.65 | EE. PWD. ABS. | 88.65 | 11.30 | Const. of 1 No. 24-R loading steel Bailey bridge(Span-150'-0") alongwith approach road | Const. of abetment completed. Bridge components received. | 6 Nos. remote habitation will be connected with Sub-divisional & Block H/Q. | By November, 2005 | |||
| Communication/Roads & Bridges | Construction of 24-R loading Portable steel Bailey bridge over Dulaicherra on the road from Dulubari to Kulai via Kekumacherra and Ram Ratan para under Ambassa Block(Span 130'-0'') | 79.26 | 79.26 | EE. PWD. ABS. | 79.26 | 65.53 | Const. of 1 No. 24-R loading steel Bailey bridge(Span-130'-0") alongwith approach road | Const. of abetment completed. Bridge components received and being erected. Work of approach road in progress. | 2 Nos. remote habitation will be connected with district H/Q via Sub-divisional & Block H/Q.1039 nos. people will get benefits. | By November, 2005 | ||
| Construction of road from Noagaon to Birjabari( length- 4.50 KM) including 24-R loading portable steel bailey bridge (Span 150'-0'') over Birjabari chera under Salema Block. | 121.52 | 121.52 | EE. PWD. ABS. | 121.52 | 75.45 | Const. of 1 No. 24-R loading steel Bailey bridge(Span-150'-0") and formation 4.50 KM of road alongwith brick soling | Const. of abetment & launching of bridge completed. Formation of works completed.Brick soling works in progress. | 4 Nos. habitation will be connected with district H/Q via Sub-divisional & Block H/Q. | By January, 2006 | |||
| Communication/Roads & Bridges | Construction of 2 nos. 24-R loading portable steel bailey bridge on the road from Vulangbasa to Dalapati para under Dumburnagar Block (Span 1x100'-00'' and 1x80'-0'') | 67.54 | 67.54 | EE. PWD. ABS. | 67.54 | 63.79 | Const. of 2 Nos. 24-R loading steel Bailey bridge(Span-1x100'-0" & 1x 80'-0") alongwith approach road | Launching of Bailey bridge completed. Works of approach road are in progress. | 8 Nos. remote habitation will be connected with Sub-divisional & Block H/Q.1843 nos. people will get benefits. | By November, 2005 | ||
| Construction of 3 nos 24-R loading Portable steel Bailey bridge from Lalcherra to Chiching cherra under Manu Block(Span 1x100'-00'' and 2x80'-0'') (I No. RCC slab culvert) | 100.36 | 100.36 | EE. PWD. KGT | 100.36 | 58.00 | Const. of 3 Nos. 24-R loading steel Bailey bridge(Span-1x100'-0" & 2x 80'-0") and 1 No. RCC slab culvert alongwith approach road | Bailey bridge 2 Nos.(span-100' & 80') including 1 no. slab culvert completed. Abetment of rest 1 No.(span-80' ) Bailey bridge completed and erection of bridge components in progress. | 8 Nos. remote habitation will be connected with Sub-divisional & Block H/Q.1501 nos. people will get benefits. | By December, 2005 | |||
| Construction of 3 nos 24-R loading Portable steel Bailey bridge on the road from Manik pur to Madhu Kumar under Chawmanu Block(Span 1x100'-00'' and 2x80'-0'') | 100.36 | 100.36 | EE. PWD. KGT | 100.36 | 53.00 | Const. of 3 Nos. 24-R loading steel Bailey bridge(Span-1x100'-0" & 2x 80'-0") alongwith approach road | Bailey bridge 1 No.(span- 80' ) completed. Rest 2 (two) Nos. in progress. | 5 Nos. remote habitation will be connected with Sub-divisional & Block H/Q. 1854 nos. people will get benefits. | By March, 2006 | |||
| Sub-Total:- | 1031.83 | 1031.83 | 1031.83 | 554.69 | ||||||||
| Total:- | 1789.66 | 1409.36 | 1398.57 | 747.33 | ||||||||